2017 Pavement Rehabilitation Program in Ward 13

2017 Pavement Rehabilitation Program in Ward 13

By Diane Colley-Urquhart on March 2017

The City of Calgary’s Roads Business Unit has finalized the annual Pavement Rehabilitation Program schedule for 2017. I am pleased to announce that there are roads in Ward 13 that have been selected for pavement rehabilitation and repair throughout the upcoming summer months. Roads strives to keep Calgarians moving, and infrastructure operating at peak efficiency. This program supports the objectives in Action Plan 2015 - 2018 as well as the achievement of performance measurements such as the percentage roadway pavement in good or very good condition (2016 - 78%, 2015 – 81%). Roads is making strides in enhancing how the Pavement Rehabilitation Program[...]

Read More
14 Street / Glenmore Trail Pedestrian Bridge Railing Improvements

14 Street / Glenmore Trail Pedestrian Bridge Railing Improvements

By Diane Colley-Urquhart on January 2017

Last year as I cycled around the south end of the city, I came across some safety hazards on the 14th  Street / Glenmore Trail pedestrian bridge where I felt a couple of safety measures were necessary. I snapped a quick video and had called upon the Roads team to inquire whether any safety adjustments could be implemented here to prevent any near misses or accidents from happening.  I am so pleased to announce that as of this week, a safety railing and a sign have both been installed here at this pedestrian bridge. The Bridges crew installed a section of[...]

Read More
SW BRT Project / ATCO's Natural Gas Pipelines Update

SW BRT Project / ATCO’s Natural Gas Pipelines Update

By Diane Colley-Urquhart on January 2017

In the coming weeks, ATCO Gas employees or contracted crews will be completing work in your neighbourhood relating to the installation of new low-pressure gas lines and relocating high-pressure natural gas lines away from residential areas to non-residential areas alongside ring roads (Transportation Utility Corridors). This project is part of ATCO’s Urban Pipeline Replacement Program and is necessary to improve Calgary’s natural gas distribution system and meet growing demands for safe and reliable natural gas service for Alberta’s largest centres. As with all municipal infrastructure construction projects, ATCO continues to work with the City of Calgary administration to coordinate construction[...]

Read More
Anderson Pedestrian Overpass Update

Anderson Pedestrian Overpass Update

By Diane Colley-Urquhart on July 2016

I would just like to take the time to update you on the Anderson Pedestrian Overpass on Anderson Road S.W. near 37 Street S.W. With construction well underway, we are seeing much more infrastructure in our City's SW. With the bridge foundations complete and retaining walls nearing completion, the main steel arch of the overpass has been delivered and is undergoing final inspection and painting. The City plans to install the steel arch and concrete deck on July 23, from 9pm to 6am. As such, Anderson Road S.W. between 24 Street and 37 Street will be fully closed during this[...]

Read More
South West Calgary Ring Road Update: Work Schedule

South West Calgary Ring Road Update: Work Schedule

By Diane Colley-Urquhart on July 2016

As we approach the start of the Government of Alberta’s construction on the Southwest Calgary Ring Road (SWCRR) in late 2016, I am pleased to announce to my constituents that The City has begun work on its SWCRR-related projects. With each City project having its own timeline over the next four years, I will be updating and talking with communities and residents throughout the different design and construction phases. The goal is to complete this work before fall 2021, when the Government of Alberta is schedule to open the SWCRR. Here’s an update on The City’s projects and their timelines:[...]

Read More